What the designer checks on a visit
The designer looks at everything the owner will see and touch. A typical visit covers:
- Setting out. Walls, niches, door positions and ceiling heights against the drawings.
- Joinery and stone. Panel layouts, joints, grain direction and edge details, checked against approved samples.
- Lighting positions. Whether the points sit where the lighting plan puts them, before the ceilings are closed.
- Finishes and colour. Paint, plaster and tile against the approved sample, ideally in the real light of the room.
- Fittings. Handles, taps, switches and sanitaryware against the specification.
Anything hidden behind a wall, such as pipework, wiring or structure, is not the designer's to certify. Those belong to the contractor and to licensed local professionals. The designer's job is to make sure the visible result and the technical drawings agree.
Why timing matters
A visit is most useful before something is covered up. First fix, before plastering, and before joinery and stone are installed are the moments when a correction costs hours. After installation the same correction means removing finished work. That is why the visit schedule is set around construction phases, not spread evenly across the calendar.
What a visit produces
A visit that leaves no record changes little. Ours ends with a short written note: what was checked, what is correct, what must change, who owns each item and by when. Many projects also get a weekly report that sets planned progress against actual progress, with photographs. The owner can follow the build from another city without reading a drawing.
Supervision, project management and contract administration
These are related but different jobs:
| Role | Answers for | Output |
|---|---|---|
| Design supervision | Match between design and result | Visit notes, clarifications, sample approvals |
| Project management | Budget, schedule, orders, coordination | Budget plan, weekly report, change log |
| Contractor | The construction itself | Programme, works, warranties |
On larger UK projects a contract administrator, often an architect or surveyor, certifies the contractor's work under the building contract. The British Institute of Interior Design notes that how far an interior designer takes part in implementation depends on the appointment: on a large project with an architect and a main contractor the designer may have limited input, while a lead designer often coordinates all works. So it is worth asking exactly what is included. For the wider role, see what project management covers.
Supervising a project from a distance
Supervision does not require the owner on site, and it can be partly remote. With a local project manager on site, the design team stays on call by email and video, and visits at agreed points. Visit frequency rises towards handover, often to two or three a month, when details and finishes matter most. On a city project with the team close by, visits can be weekly or more.
Switzerland is a good example of the split. There local engineering and construction teams handle pipework, structure and hidden services, while our team looks after every visible and touchable element and the technical specification. The two sides exchange drawings so that nothing is built twice.
Changes and delays on site
Something always changes: a wall hides a pipe, a supplier discontinues a finish, a delivery slips. On one villa a stone delivery moved the schedule back by three months, which is why orders are tracked against the building programme from the start. Supervision is where such changes are recorded, priced and approved, rather than agreed in passing on site.
Handover and the defects period
Before handover the team walks the home room by room and lists what is unfinished. On construction projects, practical completion is normally certified by the contract administrator, and certifying it starts the defects liability period, which typically lasts six to twelve months. A list of minor items to be put right afterwards is standard practice, but defects that are apparent should not be left to that list. Check your own contract for the exact terms.
How supervision is usually charged
Models vary: a monthly retainer, an hourly rate, or a fee per visit, with travel on top. We do not publish prices. The proposal states how many visits are included and what triggers extra ones.
Questions to ask before you sign
- How many visits are included, and at which stages?
- Who attends: the designer, a project manager, a procurement lead?
- What do I receive after each visit?
- Who has authority to approve a change on site, and how is it priced?
- Who handles structure, services and compliance? Licensed local professionals should.
Frequently asked questions
Is design supervision the same as building control?
No. Building control checks that work meets building regulations and is a separate process run by the authorities. Design supervision checks that the finished interior matches the design.
Do I need supervision if the contractor is good?
A good contractor builds well to the drawings, but only the designer knows the intent behind each detail. On premium projects, where one wrong joint in stone or joinery is expensive, the visit pays for itself.
Can supervision be done remotely?
Partly. A local project manager covers day-to-day matters, the designer is on call and visits at agreed stages.